Project Overview
Client
Provence Power Grid
Location
Marseille, France
Scale
120 RMUs + 200 Distribution Boxes
Date
2023-09
Challenge
France's environmental regulations required phasing out SF6 switchgear. The client needed a large batch of eco-friendly RMUs to modernize Marseille's aging distribution network.
Our Solution
We supplied 120 units of SF6-free clean air insulated RMUs and 200 low-voltage distribution boxes, all meeting the latest EU environmental standards and IEC 62271.
Supplied Products
SF6-free Ring Main UnitDistribution Box
Key Results
100%
SF6 Eliminated
320 units
Equipment Deployed
99.8%
Network Reliability